Glass House
Infrastructure

Glass House

New Canaan· 2023·City Infrastructure Authority
8,200 sqftArea
8 monthsDuration
2023Completed
HeritageStructuralCivil

Overview

Full structural restoration of the 1940s Central Bridge, including new concrete decking, updated railing systems, and waterproofing. A technically complex heritage project completed with zero traffic disruption.

The Challenge

The 1940s bridge required full structural remediation while remaining open to traffic — a constraint that demanded precision staging and round-the-clock coordination with city transport authorities.

Our Solution

We developed a three-stage lane-closure schedule, working one third of the deck at a time, allowing two lanes of traffic to remain open at all times. Night shifts handled the noisiest concrete breaking work.

Project Highlights

  • 01Heritage designation maintained throughout
  • 02Zero traffic closures — phased works only
  • 03Full concrete deck replacement and waterproofing
  • 04New stainless-steel heritage-style railings
  • 05100-year design life achieved

Project Info

Client
City Infrastructure Authority
Type
Infrastructure
Location
New Canaan
Year
2023
Size
8,200 sqft
Duration
8 months

Interested in a similar project? Let's discuss how we can bring your vision to life.

Start a Similar Project

Project Gallery

Glass House - image 1
Glass House - image 2
1 / 2

Start Your Project

Have a Project
In Mind?

Let's build something you'll be proud of. We respond within 24 hours.

Contact Us Today